Substation nears commissioning for Karlovac's new factory
FEAL Group, a leading company from Široki Brijeg, Bosnia and Herzegovina, is nearing the completion of its new factory in Karlovac, Croatia.
This state-of-the-art facility will specialize in extrusion, powder coating, and machining of construction profiles for the European Union market.
As part of this landmark project, we were entrusted with the supply and installation of a 3 x 1000 kVA transformer substation, delivering a comprehensive turnkey solution.
This included not only the substation itself but also its integration with the neighboring Elektra Karlovac infrastructure. The installation features medium-voltage VDAP 24 switchgear, low-voltage 1NBO switchgear, a compensation cabinet, and high-performance transformers.
Our project partners, KONČAR – Distribution and Special Transformers, contributed with the delivery of advanced transformer solutions, ensuring top-tier performance.
Set to be commissioned by the end of April 2024, this substation will play a pivotal role in powering FEAL’s new facility.