Generator successfully commissioned at St. Pantaleon HPP
In November 2020, we were awarded a contract to revitalize the generator at the St. Pantaleon HPP.
The project aimed to increase the generator’s capacity from 31.4 MVA to 34 MVA by installing a new stator and a brushless excitation system provided by KONČAR – Electronics and Informatics. The scope also included the inspection and cleaning of existing components, reassembly, and the provision of spare parts and staff training.
Following the successful commissioning in May 2022 and the completion of the trial run, the 36-month warranty is now in effect.
In spite of the obstacles posed by stringent COVID-19 regulations, such as quarantines and self-isolation periods, we successfully delivered the new stator and completed all on-site work within the scheduled timeline—a result acknowledged and appreciated by the customer.
After the successful completion of this project, we now have six active contracts in the Austrian-German market, along with several offers in the pipeline.